Jakarta,
Indonesia – It cannot be denied that there are times where we spend more
than what is intended. Yes, it also happens in construction projects. Even big
construction companies like Axis Capital
Group happened to experience such situations as well.
During the execution of a
project, procedures for project control and record keeping become indispensable
tools to managers and other participants in the construction process. These
tools serve the dual purpose of recording the financial transactions that occur
as well as giving managers an indication of the progress and problems
associated with a project. The problems of project control are aptly summed up
in an old definition of a project as "any collection of vaguely related
activities that are ninety percent complete, over budget and late."
Sometimes, we ask where our plans had gone overboard.
Better take note of these main types of estimating issues to prevent
complaints:
• Omissions: These are items accidentally
left out of the estimate – either soft costs (permits, fees, etc.) or hard
construction costs. Omissions may be due to items missing from the plans and
specs that were, therefore, not included in the estimate and bid.
• Wrong assumptions: These are items that
you assumed were covered under a contractor’s or subcontractor’s bid, but
aren’t. Or you may have assumed that a standard septic system would be
approved, but a $30,000 mound system is required. Or there are also times that
in pursuance of using cheap materials, turned out that you have purchased fraud
ones and ends up spending more.
• Inadequate allowances: You may get an
estimate from a contractor or subcontractor with a material allowance that’s too
low, a very common problem.
• Price changes: Material cost or labor
costs may rise between the estimate and the project.
• Unclear or incomplete plans and
specifications: The absence of clear plans leaves much room for
disagreement about what, exactly, was bid on. This can lead to change orders
and extra costs for extra work.
• Cost-plus bids: Unless you have a
guaranteed maximum, the final cost is unknown, and often more than you
estimated.
• Job-site surprises: hidden conditions
(insect damage or wood decay in remodeling, underground ledge or water
problems, etc.) In some cases, these could and should have been detected by
more diligent investigation.
• Construction/design errors: If you
build something wrong, have to tear it out and build it again, you may be able
to get someone else to pay – the architect, a sub, a supplier – but most likely
you’ll end up paying for it twice.
• Owner changes: You, the owner, may
decide to use better windows, roofing, flooring, etc., during the project; or
decide to move walls, windows, etc., after installation.
No comments:
Post a Comment